June 5, 2019

A claim for specific performance of a real estate contract.

The elements of the cause of action are that the plaintiff substantially performed its contractual obligations, and was ready, willing and able to perform its remaining obligations; that the defendant was able to convey the property; and that there is no adequate remedy at law.

Breskin v. Moronto, NY Slip Op 04126(2d Dep't May 29, 2019)

Here is the decision.